Adobe AD0-E903 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Execute: This section evaluates the skills of project execution managers, focusing on understanding and implementing milestones within a project. It includes creating Workfront Single Use Approvals and recognizing when these approvals are required. The section also reviews how various data types are utilized by the system and what information they provide to project managers.
Topic 2
  • Closeout: This part of the exam tests the skills of project closeout specialists, concentrating on the activities needed to conclude projects. It involves determining the necessary actions based on object statuses and selecting appropriate reports and reporting elements for modifying task lists or reports. Additionally, it addresses the use of wildcards in reporting and identifying project elements that indicate project success.
Topic 3
  • Intake and Planning: This part of the exam assesses the expertise of project managers and planners in managing project intake and planning. It involves identifying various ways to receive notifications of work requests and reviewing custom data to decide on suitable actions. This section also covers understanding necessary sharing permissions for different activities and configuring task settings within specified time frames.

 

NEW QUESTION # 43
Which field is used to create a milestone step on a milestone path in the Setup area?

  • A. Key
  • B. Status
  • C. Description

Answer: A

Explanation:
In Adobe Workfront, when creating a Milestone Step within the Setup area, the Key field is essential as it serves as a unique identifier for each milestone step. It is used to define the specific step within a milestone path that can be associated with tasks in a project. The Status and Description fields are not used for creating the milestone step itself but are more relevant for defining attributes or metadata.


NEW QUESTION # 44
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?

  • A. There are incomplete approval workflows on one or more tasks. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.
  • B. The task status needs to be updated to Done even though the percent complete is at 100%. The Project Owner could filter the project task list for incomplete tasks and check the task status to determine which tasks are not complete.
  • C. There are incomplete issue predecessors that need to be resolved. The Project Owner can navigate to the project issues section in the left navigation pane to see the incomplete items.

Answer: B

Explanation:
Even if the task shows 100% complete, the Status of the task may still be listed as something other than "Done." Workfront requires that both the Status and the Percent Complete indicate the task is fully completed before the project can be marked as complete. The Project Owner can filter for tasks that are not marked as "Done" and update their statuses accordingly.


NEW QUESTION # 45
What occurs when an individual enters a new commit date that is after the original planned date of a task?

  • A. The Project Owner is notified whether this change will impact the Project Timeline.
  • B. The assignee of any task that has the original task set as a predecessor is notified.
  • C. The Planned Completion Date of the task automatically changes to match the new Commit Date.

Answer: C

Explanation:
When a user updates the Commit Date to a date later than the original planned date in Adobe Workfront, the Planned Completion Date of the task is automatically updated to reflect the new commit date. This feature ensures that the timeline is adjusted based on the most current commitment by the task assignee, which can then impact downstream tasks and the overall project schedule.
This change streamlines project planning and helps keep task dependencies aligned with realistic completion expectations.


NEW QUESTION # 46
What item, when shared with a user, can never give that user inherited permission to a project?

  • A. Task
  • B. Portfolio
  • C. Report

Answer: C

Explanation:
Adobe Workfront, permissions can be inherited through various objects like projects, portfolios, or tasks when shared with users. However, when sharing a report, the permissions do not cascade to related items like projects or tasks within that report. This is because reports are generated views and do not directly control object-level permissions. A report can be shared to allow a user to see data within the report, but it will not grant them inherited permissions to the underlying projects or tasks displayed in that report.


NEW QUESTION # 47
A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

  • A. Project Details
  • B. Billing Records
  • C. Business Case

Answer: A

Explanation:
In Adobe Workfront, the Project Details section is where you can find critical information about the financial aspects of a project, including the fixed revenue and costs. This section includes details such as budgets, financials, and other related data. The Business Case primarily contains the justification or rationale for the project, while Billing Records pertain to invoicing and payment tracking, not necessarily fixed project costs and revenue.
For accurate financial tracking and reporting, the Project Details page is the go-to source for project managers to monitor and update financial data.


NEW QUESTION # 48
A project sponsor has asked to see a summary of all projects that they are the sponsor of which were completed in the past year. The project sponsor wants to see the information grouped by the month the project was completed. What steps should the project manager take to create this view?

  • A. Visit the Reports page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month."
  • B. Visit the Reports page and create a Project Sponsor report. In the filter, update the actual completion date value with custom dates for the past year and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the planned completion date. In the Group Dates by field, select "month of year."
  • C. Visit the Dashboards page and create a Project report. In the filter, update the actual completion date value to "past year" and update the Project Sponsor ID field to the project sponsor's name. In the grouping tab, add a grouping for the actual completion date. In the Group Dates by field, select "month of year."

Answer: A

Explanation:
The best approach is to generate a Project Report in Workfront, where the report filters the Actual Completion Date for the past year and groups projects by the Sponsor and the month of completion. This allows the sponsor to see exactly which projects they sponsored and when they were completed within the selected timeframe. Grouping by month provides a clear visual of the completion timeline.


NEW QUESTION # 49
A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?

  • A. Change the Task Duration Type to Effort Driven
  • B. Change the Task Constraint to As Soon As Possible
  • C. Change the Task Duration Type to Calculated Work
  • D. Change the Task Constraint to Fixed Dates

Answer: C

Explanation:
When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to "Calculated Work" allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.


NEW QUESTION # 50
Which element is defined as a reportable variable determined by the relationship between the planned, projected, and estimated dates of the project?

  • A. Status
  • B. Condition
  • C. Progress Status

Answer: B

Explanation:
In Adobe Workfront, Condition is the reportable variable that is determined by the relationship between the Planned, Projected, and Estimated Dates. The Condition field reflects whether a project is On Target, At Risk, or In Trouble based on how its actual progress aligns with the planned schedule and dates. It allows project managers and stakeholders to quickly assess the health of the project.


NEW QUESTION # 51
The marketing team should begin working on a task on September 23, complete it within 2 weeks and take approximately 10 hours over that time span to execute the deliverable.
Which task settings need to be configured to meet these requirements?

  • A. The Task Constraint should be set to Start Date of September 23 with Planned Hours set to 10 hours and Issue Duration set to 2 weeks.
  • B. The Task Constraint should be set to Must Start On with Planned Time set to 2 weeks and Duration set to 10 hours.
  • C. The Task Constraint should be set to Must Start On with Planned Hours set to 10 hours and Duration set to 2 weeks.

Answer: C

Explanation:
In Workfront, setting the correct task constraint and planned hours ensures that the task starts on the intended date (September 23) and allows the team to track the time allocated (10 hours) over a 2-week duration. "Must Start On" ensures the task begins exactly on the planned start date.


NEW QUESTION # 52
What parent object can have child objects?

  • A. Issue
  • B. Project
  • C. Portfolio

Answer: C


NEW QUESTION # 53
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

  • A. Status
  • B. Actual Completion Date
  • C. Progress Status

Answer: A

Explanation:
Even though tasks may be marked as 100% complete, their Status may still be listed as incomplete in reports if the task's status has not been updated to "Completed." The Status column provides insight into the current state of the task, which helps identify if the task is still listed as "In Progress" or another incomplete status despite being marked as fully complete. Adding this column clarifies why the task appears in the Incomplete Tasks Report.


NEW QUESTION # 54
Which date type on tasks can a project manager manually modify?

  • A. Estimated
  • B. Planned
  • C. Projected

Answer: B

Explanation:
In Adobe Workfront, Planned Dates are the dates that project managers can manually modify. These dates represent the schedule that the project is expected to follow and can be adjusted based on project needs. Estimated and Projected Dates are automatically calculated by the system based on task progress and dependencies, and these cannot be manually modified directly by a project manager. The Projected date is influenced by changes in the actual completion rate of tasks, whereas the Planned Date is the baseline schedule.


NEW QUESTION # 55
A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.
What should the team lead use to organize these projects to allow them to be tracked together?

  • A. Layout template
  • B. Group
  • C. Program

Answer: C

Explanation:
In Workfront, a "Program" is used to group related projects that share a common objective or need to be tracked together, such as adherence to budget and timeline. Programs allow for collective reporting on these projects, making it easier for team leads to monitor progress, manage resources, and report on key performance indicators (KPIs) across multiple projects.


NEW QUESTION # 56
An organization has created unique data fields relevant to their projects. Starting by navigating from a project's landing page, where is this data found?

  • A. Business Case > Project Info
  • B. Project Details > Custom Forms
  • C. Project Details > Overview

Answer: A

Explanation:
In Workfront, custom data fields created for projects are typically found within the "Business Case" section, specifically under "Project Info." This area houses key project information and unique custom fields that are relevant to the project's setup. The "Project Details" section is more focused on task-related information and the overall summary of the project.


NEW QUESTION # 57
What parent object can have child objects?

  • A. Issue
  • B. Project
  • C. Portfolio

Answer: C

Explanation:
In Workfront, a "Portfolio" is a parent object that can contain multiple programs and projects. Each Portfolio can have a hierarchy of child objects such as programs, which further break down into projects. A project, while it contains tasks and issues, is considered a child within the larger hierarchy of a portfolio. Issues, on the other hand, are typically linked to tasks or projects but are not used as parent objects. This hierarchy enables Workfront users to organize and manage their work across various levels.


NEW QUESTION # 58
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

  • A. Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.
  • B. Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.
  • C. Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.

Answer: B

Explanation:
To create a custom report in Workfront that focuses on issues logged to projects, the project manager needs to create a new Issue report from the Reports page. By applying a filter based on the Project Owner ID and grouping the report by project name, they can track all the issues associated with the projects they own. This approach provides clear visibility into project-related issues.


NEW QUESTION # 59
A client has negotiated a discounted billing rate for video editing in a specific initiative.
How can the project manager override the default billing rate for the Video Editor within a project?

  • A. Temporarily change the billing rate for the Video Editor in the Workfront system, and then reset it once the client has been billed.
  • B. Add a new billing rate to all tasks that involve video editing.
  • C. Add a new billing rate within the project.

Answer: C

Explanation:
In Workfront, billing rates can be customized for individual projects. To apply a negotiated rate for the Video Editor role within a specific initiative, the project manager can add a new billing rate at the project level. This ensures that the rate is applied only to tasks within the project and does not affect the default system-wide rate for other projects.


NEW QUESTION # 60
Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?

  • A. At Risk
  • B. Behind
  • C. On Time

Answer: A

Explanation:
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as "At Risk." This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.


NEW QUESTION # 61
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

  • A. Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.
  • B. Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.
  • C. Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.

Answer: B

Explanation:
To create a custom report in Workfront that focuses on issues logged to projects, the project manager needs to create a new Issue report from the Reports page. By applying a filter based on the Project Owner ID and grouping the report by project name, they can track all the issues associated with the projects they own. This approach provides clear visibility into project-related issues.


NEW QUESTION # 62
The second task in a project should be completed within 48 hours and needs to begin 5 business days after the first task is completed.
Which task settings should be configured to meet these requirements?

  • A. The task Duration should be set to 2 days. A predecessor with a Finish-Start Dependency Type should be added to the second task with a lag of 5 days.
  • B. Planned Hours should be set to 48 hours. A predecessor with a Finish-Start Dependency Type should be added to the first task with a lag of 5 days.
  • C. The task Duration should be set to 48 hours. A predecessor with a Start-Finish Dependency Type should be added to the second task with a lag of 5 days.

Answer: A

Explanation:
In Adobe Workfront, to configure tasks according to the requirement of the second task beginning 5 business days after the first task, you need to set the appropriate "Duration" and use "Finish-Start" dependencies. The task's duration is key to determining the time allowed for its completion. The "Finish-Start" dependency ensures that the second task begins only after the first is finished, and a lag can be set to introduce a delay, such as 5 business days. Setting a "Finish-Start" dependency with a lag allows for proper scheduling of tasks in sequence without overlapping.


NEW QUESTION # 63
Which project Condition is set when the Progress Status of the project is Behind or At Risk?

  • A. At Risk
  • B. Late
  • C. In Trouble

Answer: A

Explanation:
In Adobe Workfront, when a project's progress status is marked as Behind or At Risk, the project condition is set to At Risk. This indicates that the project may not meet its deadline or performance metrics, signaling to the project team and stakeholders that corrective action may be necessary. The "In Trouble" status is reserved for more severe cases, and "Late" is generally used for tasks or projects that have passed their planned completion dates without being finished.
The At Risk status allows proactive intervention to address potential issues before they escalate into bigger problems.


NEW QUESTION # 64
......