NEW QUESTION 18
How would you define pegging in the context of Advanced Planning?

  • A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
  • B. An evaluation that is ordered according to the bill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
  • C. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
  • D. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.

Answer: B

 

NEW QUESTION 19
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

  • A. Float before production
  • B. Pick/pack time
  • C. Wait time
  • D. Move time
  • E. Queue time

Answer: B,C,E

 

NEW QUESTION 20
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. To determine the work in progress along the production line
  • B. To reduce the totalproduction lead time for along production line
  • C. To stage different components for a production line simultaneously
  • D. To provide timely updates of inventory management for the staged components

Answer: A,D

 

NEW QUESTION 21
Which transaction code can you use in SAP S/4HANA to enter and display goods movements?

  • A. MBNL
  • B. MIGO
  • C. MMBE
  • D. MBO2

Answer: B

 

NEW QUESTION 22
You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?

  • A. Top of Red
  • B. Top of Yellow
  • C. Top of Red Base
  • D. Top of Green

Answer: D

 

NEW QUESTION 23
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.

  • A. Scrap percentage
  • B. Quantity
  • C. Item type
  • D. Installation point

Answer: B,D

 

NEW QUESTION 24
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

  • A. It is converted into a production order.
  • B. It is converted into a schedule line.
  • C. It is converted into a planned order.
  • D. It is converted into a reservation.

Answer: D

 

NEW QUESTION 25
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.

  • A. Validity dates
  • B. Task list group number
  • C. BOM status
  • D. Lot sizes
  • E. Work center hierarchy

Answer: A,C,D

 

NEW QUESTION 26
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?

  • A. Planning with final assembly (40)
  • B. Make-to-order production (20)
  • C. Make-to-stock production (10)
  • D. Planning without final assembly (50)

Answer: A

 

NEW QUESTION 27
What are properties of MRP Live? There are 2 correct answers to this question.

  • A. The code is written in SQL Script
  • B. Data is read sequentially from the database tables
  • C. It uses the same BAdis as classic MRP
  • D. It is executed on the database server

Answer: A,D

 

NEW QUESTION 28
Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements? Note:There are 2 correct answers to this question.

  • A. In-house production time
  • B. Planned delivery time
  • C. Total replenishment lead time
  • D. Operation duration

Answer: A,B

 

NEW QUESTION 29
You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?

  • A. Consumption-based planning
  • B. Manual planning without check
  • C. Forecast planning
  • D. Material requirements planning

Answer: A

 

NEW QUESTION 30
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.

  • A. Capacity Requirements Planning (CRP)
  • B. Integrated Business Planning (IBP)
  • C. Material Requirements Planning (MRP)
  • D. Supply Chain Management (SCM)

Answer: B,D

 

NEW QUESTION 31
In your plant, MRP is activated. Which options do you have to exclude a material from the MRP run?Note:
There are 2 correct answers to this question.

  • A. Use a specific MRP controller.
  • B. Use a specific MRP type.
  • C. Use a specific material status.
  • D. Use a specific material group

Answer: A,B

 

NEW QUESTION 32
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.

  • A. Production version
  • B. Material
  • C. Plant
  • D. Work center

Answer: B,D

 

NEW QUESTION 33
Why would you use phantom assemblies? Note: There are 3 correct answers to this question.

  • A. To reduce the number of material masters
  • B. To increase the number of planning levels
  • C. To make the assignment of components easier
  • D. Tosimplify the structure of bills of material
  • E. To reduce the number of changes required in bills of material

Answer: C,D,E

 

NEW QUESTION 34
You want to integrate an existing planned order into Advanced Production Planning. Which report do you use? Please choose the correct answer.

  • A. /SAPAPO/PPDS_DELTA_ORD_TRANS
  • B. /SAPAPO/CREATE_LOCATION
  • C. /SAPAPO/UPD_LOC_SP_PL
  • D. /SAPAPO/CURTO_CREATE

Answer: A

 

NEW QUESTION 35
You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?

  • A. Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator
  • B. Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator
  • C. Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator
  • D. Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.

Answer: D

 

NEW QUESTION 36
A resource was created in SAP S/4HANA PP/DS through the internal CIF integration and named "W1904_1000_001". What does the suffix 001 in the resource name represent?

  • A. Available capacity version
  • B. Number of individual capacities
  • C. Capacity category
  • D. Work center category

Answer: C

 

NEW QUESTION 37
How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality?

  • A. By providing future demands from demand figures in the past
  • B. By providing cross-plant planning and deployment
  • C. By providing replenishment proposals with exact times
  • D. By providing multilevel material requirements planning

Answer: C

 

NEW QUESTION 38
You are using the document management system (DMS) . Where should the DMS document links be assigned, to have them automatically copied to production orders?
There are 2 correct answers to this question.

  • A. Routing header
  • B. Bill of material
  • C. Work center
  • D. Material master

Answer: B,D

 

NEW QUESTION 39
You want to perform capacity availability checks on your production orders. What must be set for this to occur? Note: Thereare 2 correct answers to this question.

  • A. Checking rule and group must be assigned.
  • B. PRT Availability check must be set.
  • C. Indicator Relevant for finite scheduling must be set.
  • D. Checking control must have an overall profile assigned in customizing.

Answer: C,D

 

NEW QUESTION 40
......